News Of The Company
Overlook of the Factory
Rotary Kiln(3200 TPD Clinkers)
Cement Mill(2×75T/h Vertical Mill)
Central Control Room
Waste Heat Cogeneration Unit(4.5MW)
Ignition of Kiln has been successfully achieved on Aug 18 2014 in Cambodia Cement Chakrey Ting Factory, followed by startup of cement mill on Aug 30 2014 when cement being produced. After a period of 20 months EPC works commencing from Dec 28 2014, construction of the Factory and the kiln ignition have been fulfilled earlier than planned. In the current onging commissioning, product indicators and guaranteed performance are to be further observed and improved.